Service 03 of 07 · Develop

The State is paid first.
Then everyone else, in order.

Build-operate-transfer and design-finance-build-operate-transfer concessions, with risk placed where it is controlled, fees paid on proof and the keys handed back. The split shown is illustrative.

The structuresSchematic, illustrative split. A unit of fee falls basin to basin.

Structures

Two structures cover most cases, and they differ in who carries the early phases

Terms are commonly 15 to 20 years (an illustrative range). Choose a structure to see who carries each phase.

DesignFinanceBuildOperateTransferTop row: contracting authority. Lower row: partner.The asset returns to the national owner at the end of the term
Structure

Build, operate, transfer

The partner builds and operates, then transfers. The contracting authority specifies design and financing arrangements, and so keeps the risks attached to them.

Design, finance, build, operate, transfer

The partner designs and finances as well. Risk follows control from the first drawing, and the partner is paid only on a registered, verified record.

The order of payment

Each unit of fee falls in a fixed order, and unverified units earn nothing

Change the volume, the share of units that carry a verified record and the three shares ahead of the operator. The State's share is always first.

One month of registered units

Illustrative
1000
10
90%
40%
10%
5%
All units times fee, in the order they fall1 State share2 Performance reserve3 Independent auditor4 OperatorProvisional, earns nothing
0Registered fee, currency units
0Left for the operator, percent

Shares are applied in order to the registered fee. If they together exceed it, the later layers are cut first. Full instrument

Method

A concession is a timeline with a tail, and the hand-back is designed on day one

ChallengeBuildOperateHand-overBack1 Rivals may challenge2 Escrow opens at the effective datebuy-out formula fixed at signatureOperate: revenue against a reference trajectoryReference trajectoryActualUpside above it, sharedHanded backassetscodeskills
Phase 1 of 5

The route welcomes a rival

An unsolicited proposal is published with its terms, and any rival may challenge it before the contract is signed.

Phase 2 of 5

The escrow opens with the contract

Fees flow into an escrowed collection account in which the operator is not a signatory. The State's share is paid first.

Phase 3 of 5

Upside above a reference is shared

Fees are performance-at-risk against published KPIs. Revenue above a reference trajectory is split between State and partner.

Phase 4 of 5

Exit is priced before entry

Termination and buy-out formulas are fixed at signature, so no party negotiates its way out under pressure.

Phase 5 of 5

The keys are handed back free

Assets, code and skills pass to the national owner at the end of the term. The hand-over is rehearsed in the years before it.

Risk allocation

Risk goes to the party that controls it

A risk placed on a party that cannot control it is priced into the fee, or comes back as a dispute. Choose a party to see what it carries.

Carries (filled), shares (ring) or does not carry (dash). A reference allocation, adjusted for each programme.
RiskStatePartnerLenders
Design and construction cost
Technology performance
Completeness of the verified record
Change in law or tariff
Site access, permits and data links
Funding cost and tenor
Force majeure
carriessharesdoes not carry
Party

The State carries what only it controls: the law, the tariff, access to site and the data links it has agreed to open. It keeps its share first.

The partner carries build, technology and the completeness of the record. Its fee is at risk against published KPIs, and an unverified unit earns nothing.

Lenders carry the residual after equity and the reserve accounts, protected by the escrow and by a record an independent auditor can replay.

Unsolicited proposals

An unsolicited route is credible only if a rival can beat it

The route is open to competitive challenge. Choose an outcome to follow the path it takes.

Rival bidsProposal filedpublicTerms publishedopen bookChallenge windowany rivalMatch or awardper published termsEffective dateescrow opensNo rival: the published terms stand
Outcome

If no rival comes forward in the window, the terms published at the start are the terms signed. The public has seen all of them.

If a rival bids, the published terms say whether the proponent may match. Either way the contract is the product of a contest, not of a private negotiation.

State share first

The operator reads the account and never signs it

Fees are collected in an escrowed account. The operator sees every statement and signs none, and the firm never holds public money.

Registered, verified unitsEscrowed collection accountSignatories, illustrative arrangementPublic authoritysignsIndependent auditorsignsOperatorreads statements, is not a signatoryOrder of payment out1State share2Performance reserve3Independent auditor4Operator

Hand-back

Hand-back is free: assets, code and skills pass to the national owner

Local staffing rises over the term and the hand-over is rehearsed before it happens. Move through the term to see both. The term and the staffing targets are illustrative.

Local staffing target and hand-over readiness

Illustrative
18
12
0Local staffing target, percent
0Years to hand-back
  • Assets inventoried and signed
  • Hand-over rehearsal run
  • Code and models released from escrow
  • Skills transferred, national managing director in post
Year 1Hand-backLocal staffing target, illustrative, percent of the team