Instrument · Deployment planner
Ninety days is a crew count,
not a promise.
Sites fall into three waves across the first 90 days. Change the number of crews and the waves re-plan: some sites move forward, some fall off the end of the plan.
Three waves
Three waves, cut by two gates, fit inside 90 days
A programme that goes live in about 90 days is not rushed. It is divided: each wave has a window, a purpose and a gate.
Once a contract is effective, the delivery model runs in three windows. Days 1 to 30 open the data centres and the first feeds, and the academy begins. Days 31 to 60 bring every source online and reconcile it in parallel against existing filings. Days 61 to 90 produce dashboards, first statements and acceptance.
The planner turns those windows into a schedule of sites. A site belongs to the wave in which it is commissioned, so the waves are an outcome of crews and durations, never a target a site is asked to hit.
Illustrative The 90 days and the three windows come from our delivery model. Every number in the planner is an input you can change.
- Wave 1days 1 to 30Data centres, first feeds, academy opens.
- Wave 2days 31 to 60All sources feeding, parallel reconciliation.
- Wave 3days 61 to 90Dashboards, first statements, acceptance.
The planner
Crews decide which wave a site lands in, and whether it lands at all
Set the programme and the crews. Each site goes to the first crew that is free, in priority order, and the plan stops where an installation would end inside the acceptance reserve.
Inputs Illustrative
Plan across 90 days
Simulated scheduleAll 60 sites are commissioned by day 67.
Source: simulated schedule on illustrative inputs. The windows follow the delivery model: days 1 to 30, 31 to 60 and 61 to 90.
Four crew counts
The fourth crew closes the plan; the sixth leaves wave 3 empty
One programme of 60 illustrative sites, four crew counts. Scroll, and watch the blocks change wave.
Two crews leave 24 sites beyond day 90
Each crew can commission at most 18 sites before the reserve begins, so two crews cap the plan at 36. Wave 1 gets 10, wave 2 gets 16, wave 3 gets 10. The rest queue at the right of the chart, unplaced.
Three crews still leave 6 sites out
54 sites are placed: 15 in wave 1, 24 in wave 2 and 15 in wave 3. A third crew places 18 more sites than two.
Four crews commission all 60 sites by day 67
Wave 1 holds 20, wave 2 holds 32 and wave 3 holds the last 8. Crews are in use for 82 percent of the days before the reserve; the 13 days left are slack against a late delivery.
Six crews leave wave 3 empty
30 sites commission in wave 1 and 30 in wave 2. The plan ends at day 47, but crew time in use falls to 55 percent: the extra crews are paid for and wait.
Across crew counts
Crews needed climb in steps, because a crew commissions whole sites
Move the programme size and read two things: where the sites land at every crew count, and how many crews the programme needs.
Gates
Waves are cut where gates close, not on a calendar
A site is not commissioned when the crew leaves it. It is commissioned when it has passed every gate, and the programme has passed its own.
Site gates: six, passed by every site
- GATE 1ProposedThe site is on the priority list.
- GATE 2SurveyedAccess, power and path are checked on the ground.
- GATE 3DesignedThe installation design is approved for that site.
- GATE 4InstalledEquipment and interfaces are in place.
- GATE 5VerifiedThe legal-metrology body has witnessed the test.
- GATE 6CommissionedThe site is live and handed to operations.
Acceptance gates: six, passed by the programme
- A1InterfaceEvery interface meets its schedule.
- A2ComponentEach component passes its own test.
- A3IntegrationThe components work together.
- A4OperationalThe operations team runs it unaided.
- A5ServiceService levels are met on telemetry.
- A6TransferAssets, code and skills pass to the owner.
Each site passes six gates; the programme passes six acceptance gates. A wave closes when its sites have commissioned, not when a date arrives.
Site gates run site by site, so crews can work in parallel and a failed verification holds one site rather than the wave.
Acceptance gates run on the programme: interface, component, integration, operational, service and transfer. The last one passes assets, code and skills to the national owner.
Method and limits
The planner is a counting rule, and it says so
It shows what crews and durations imply. It does not forecast a programme, and no output here is a commitment.
| Rule | How the planner treats it | What a real programme adds |
|---|---|---|
| Crews | Each crew works one site at a time and is free again when the site is commissioned. | Weather, access, customs clearance and leave. |
| Order | Sites are taken in priority order by whichever crew is free first. | Priority is a decision of the public owner of the programme. |
| Wave | A site belongs to the window in which it is commissioned. | Waves are reporting windows, not separate contracts. |
| Reserve | No installation may end inside the acceptance reserve. | Acceptance gates need their own people and days. |
| Mobilisation | All crews start together after the mobilisation days. | Pre-effective preparation shortens this, at the developer’s own risk, before day one. |
| Duration | One duration for every site. | Sites differ; durations come from surveys. |
Formulas: a crew commissions floor((90 minus reserve minus mobilisation) / days per site) sites; crews needed is the programme divided by that, rounded up. Every input is illustrative and editable above.
Where this leads